Budget and Contract Tables

In Cost Management, there are two overviews of the financial information. The information is presented in tables on the Budget and Cost tabs. These tables allow you to track incoming and outgoing cash for your project.

The tables contain the same overall financial information only organized differently for your preference. There are five main sections:

How Change Orders Populate the Budget and Contract Tables

Selecting In, Out, Budget Only, or Contingency as an option for scope determines whether a change order cost item populates the budget and cost fields, or only cost.

Scope can be selected as follows:

Tip: You can customize the name of the change order scope in Change Order Settings to suit your company's needs.

The specific columns are outlined in the following sections.

Budget Columns

The values populate and move across the columns in the budget section as the budget status changes.

In the following image the colors represent the column that values appear in, based on their budget status. The value entered comes from the cost stage of the cost item.

Note: Draft, Rejected, and Void budget statuses don't appear in the table.

Cost Columns

The values populate and move across the columns in the cost section as the cost status changes.

The colors in the following image represent the column that values appear in, based on their cost status. The value entered comes from cost stage of the cost item.

Note: Draft and Void cost statuses don't appear in the table.

Forecast Columns

The values populate and move across the columns in the forecast section as the cost status changes.

Variance Columns

The values populate and move across the columns in the variance section as the cost status changes.

Note: You can customize the budget and contract tables to provide unique columns for more individual calculations. To learn more, see the Create Custom Columns article.